Lebuhraya Damansara - Puchong (LDP), Selangor Darul Ehsan |
RM 306 Million |
26-Dec-1995 |
31-Dec 1998 |
31-Dec 1998 |
LITRAK Berhad |
Projek Membina Persimpangan Bertingkat menghubungi Lebuhraya Utara-Selatan ke Hospital Sungai Buloh, Selangor Darul Ehsan
|
RM 52 Million |
16-Feb-2004 |
13-Sep-1996 |
15-Aug-2006 |
Jabatan Kerja Raya |
Projek Membina Lebuhraya Timur-Barat Fasa II Titi Karangan ke Gerik, Pakej IV dari Kupang ke Gerik, Perak Darul Ridzuan.
|
RM 16 Million |
25-Aug-2006 |
11-Feb-2007 |
08-Feb-2007 |
Jabatan Kerja Raya |
Projek Membina Jalan Sapulut - Kalabakan, Sabah
|
RM 565 Million |
02-Oct-2004 |
23-Jun-2008 |
15-May-2008 |
Jabatan Kerja Raya |
|
|
| List of Current Project |
NAME OF PROJECT |
CONTRACT VALUE |
COMMENCEMENT DATE |
COMPLETION DATE |
CLIENT |
Electrified Double Track Project - Northern Package.
The Construction, Completion, Testing Commissioning and Maintenance of the Infrastructure Works - Package N8 between Salak Utara and Ipoh, Perak. |
RM 863 Million |
18-Feb-2006 |
17-Feb-2012 |
MMC-GAMUDA JV Sdn Bhd |
|
|
|